Self-climbing formwork system puts the deadline within reach
Tekst en beeld PERI BeNeLux bv

Silver Tower, a prestigious high-rise with 40,000 m2 of office space, was built on the busy Sint-Lazarusplein, close to Brussels North railway station.
Building the tower within the 18-month deadline called for ingenious formwork systems.
Silver Tower has 8 basement levels and 32 above-ground floors, including 2 technical floors. Yet the tower had to be built in just 18 months. And CIT Blaton faced several other major challenges. Silver Tower was built in the heart of Brussels, where there was no space for setting up a construction site, positioning a tower crane or storing building materials. This called for tightly organised logistics. The design also required robust support solutions, for example for the atrium above the entrance. Thanks to PERI’s formwork methods, the 137-metre-high Silver Tower was completed on schedule.

Complex formwork and support solutions
As soon as the contract was awarded, PERI’s engineers designed the formwork systems at record speed. The formwork not only had to take the right shape, it also had to be possible to bring the elements in and out of the confined work area. This made the designs highly complex. The solution was PERI’s ACS climbing formwork (Automatic Climbing System), which enabled workers to climb safely without a tower crane and allowed the contractor to complete one floor every five days. No other formwork system would have enabled the contractor to build at this pace.

Ready to assemble on site
The bespoke formwork was manufactured in the PERI workshops in Schijndel and at CIT Blaton. Much of it was also pre-assembled there, so it only had to be put together on site. This saved CIT Blaton a considerable amount of time. Alongside the ACS climbing system, many other PERI systems were used on site, including VARIO GT 24 girder wall formwork, SKYDECK slab formwork, VARIOKIT engineering kit, PERI UP Flex Stair 75, PERI UP Flex reinforcement scaffold and MULTIPROP aluminium props.

Fast. Cost-effective. Expert.
“PERI’s ACS climbing system is lightweight, good and practical,” says Yves Uyttenhove, project manager at CIT Blaton. “The climbing formwork enabled us to meet our deadline. The formwork cycle was very short, and we made considerable savings because we did not need to use an additional crane. We also found PERI to be an expert partner. Its engineers quickly came up with solutions to highly complex problems, while meeting the requirements for construction sites and core formwork in high-rise buildings.”

Flexible formwork
For Silver Tower, the ACS system was designed so that the same formwork could be used to pour both the thick walls on the lower floors and the thinner walls on the upper floors, without significant adjustments. This also saved time and money. The climbing system featured an enclosed working platform, with the formwork positioned at different levels and suspended beneath an upper working platform. This created more working space and made construction easier.
Versatile solutions
The other systems also addressed the formwork challenges. SKYDECK slab formwork was used on the 16th, 17th and 18th floors to ensure the tower’s stability and strength. VARIOKIT was used to support the 24 inclined columns on the ground floor, while PERI UP stair towers were erected to ensure worker safety. “PERI had a solution for every problem.”
Een zakelijke vraag aan PERI BeNeLux B.V.? Neem contact op
Wie eraan werkte
Silver Tower in Brussel
- bekistingssystemen
PERI - aannemerCIT Blaton
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectSilver Tower
- OnderwerpProjects
- BedrijfPERI BeNeLux B.V.
- BedrijfCIT Blaton


















