Projects

Sint-Pieters-Woluwe Stormwater Reservoir | Innovative tunnel boring machine technology limits impact on the surrounding area Tubular stormwater reservoir to prevent flooding

Sint-Pieters-Woluwe Stormwater Reservoir | Innovative tunnel boring machine technology limits impact on the surrounding area Tubular stormwater reservoir to prevent flooding

During heavy rainfall, people in certain areas hold their breath, because if things go slightly wrong, the streets flood and water reaches homes. This is also the case in and around Sint-Pieters-Woluwe. That is why client Vivaqua commissioned the Grootveldlaan Joint Venture (BAM Contractors, Wayss & Freytag and Denys) to build a tubular stormwater reservoir beneath Grootveldlaan, with a storage capacity of 8,000 m³. The contractor is using an innovative technique based on a large-diameter underground tunnel, combined with a pumping station, access shaft and overflow. This underground installation limits the impact on the surrounding area.

Climate change is bringing more frequent sudden downpours, making stormwater management a top priority in Belgium too. During torrential rain in and around Sint-Pieters-Woluwe, the sewers in the Struybeeck Valley struggle to cope with the water. As a result, streets flood and basements are inundated. This is why the Grand Prix (7,000 m³), Herendal (7,000 m³) and Stockel (3,000 m³) stormwater reservoirs were built in the past. “These basins are designed to temporarily store large volumes of water, allowing us to regulate flows in the sewers, prevent flooding and control discharges into the natural environment,” says Dirk
Derycke, Division Manager Tunnelling & Drilling at Denys. “During heavy rainfall, the sewage flows into the basin. Once the rain has stopped, the water is pumped back into the sewer.”

The Grootveldlaan Joint Venture first built a pumping station using secant piles and a reinforced underwater concrete base slab. The tubular stormwater reservoir will follow in a second phase.

New technique using an underground tunnel

However, the risk of flooding in the area remained high, so Vivaqua decided to build a new basin on Grootveldlaan with a storage capacity of 8,000 m³. The contract was awarded to the Grootveldlaan Joint Venture, comprising BAM Contractors, Wayss & Freytag and Denys. “The dense urban development made it difficult to incorporate above-ground basins here. A large-diameter tunnel combined with a pumping station offered a solution,” says Derycke. “This innovative technique keeps the visible impact on the surrounding area to a minimum.” 

Site manager Sander Cambron explains the project: “Last year, we built a pumping station 17.40 m long, 10.90 m wide and 12.25 m deep, with 16 m-long secant piles and a reinforced underwater concrete base slab. In February 2019, we began assembling our tunnel boring machine, Petra, which is now being used to bore a 375 m-long tunnel with an internal diameter of 5.20 m. We are using 310 precast segment rings to line the tunnel, manufactured at our subsidiary in Oelegem. Early next year, a 15 m-deep access shaft will be built at the end of the tunnel, to be used for inspection and ventilation, among other purposes. The connection to the sewer network will follow by mid-2020, and the pumping station will be completed.”

The Petra tunnel boring machine, specially adapted for this project, is to bore a 375 m-long tunnel with an internal diameter of 5.2 m.

A major challenge for the engineers

Many above-ground stormwater reservoirs have already been built across the country. This is not Belgium’s first tubular stormwater reservoir, but it is the largest. “Our tunnel boring machine was first used on a project in Algeria and has been specially adapted for this tunnel,” Derycke concludes. “Unlike other installations, we are working with a short pumping station. The tunnel also has a 1% gradient, so no sludge is left behind. The project in Sint-Pieters-Woluwe is therefore a major challenge for our engineers.” ν

Vraag over dit verhaal? Stel je vraag

Wie eraan werkte

Tubulair stormwaterbekken Grootveldlaan in Sint-Pieters-Woluwe

  1. bouwheerVivaqua
  2. THV GrootveldlaanBAM Contractors
  3. THV GrootveldlaanWayss & Freytag
  4. THV GrootveldlaanDenys

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • ProjectTubulair stormwaterbekken Grootveldlaan
  • OnderwerpProjects
  • BedrijfVivaqua
  • BedrijfBAM Contractors
  • BedrijfWayss & Freytag
  • BedrijfDenys
Deel dit artikel

Advertentie

Volgen op Beton & Staalbouw

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.