Smart collaboration between Xella and Van Wijnen saves considerable time on high-rise project

Thanks to smart collaboration between developer-builder Van Wijnen, supplier Xella, Bestcon, Faber and various building services contractors, construction of the residential tower De Hoge Regentesse in The Hague has been significantly accelerated. Compared with a conventional fit-out process, the 23 floors are estimated to be completed around three months earlier. The time savings come from positioning packs of Ytong aerated concrete internal wall panels at a very early stage, before the floor is topped with foamed concrete. This creative solution enables Van Wijnen to complete one floor per week.
Creative solution cuts fit-out time by months at The Hague residential tower De Hoge Regentesse
De Hoge Regentesse is a 23-storey residential tower just south of The Hague city centre. It is being built on a very small site, placing considerable demands on construction logistics. To minimise disruption to residents, traffic and businesses in the city centre, Van Wijnen has opted for a fast structural system in which a centrally positioned crane installs precast concrete floor, wall and façade elements.
Fast structural work, fast fit-out
A way to speed up the fit-out was also sought. Van Wijnen’s aim was to complete one floor per week. Xella was involved in discussions with Van Wijnen at an early stage. Working with the building services contractor, the parties came up with an unusual solution: positioning packs of Ytong aerated concrete wall panels on Ytong blocks before pouring the foamed concrete screed. “This means that, once the screed has cured and an initial waterproofing layer has been applied on the floor above, the walls can be installed straight away,” says Xella business developer Bas Peereboom.
More efficient supply
Because aerated concrete is not sensitive to moisture, the panels can be delivered during the structural phase. As well as allowing installation to start straight away, this brings other benefits, says Van Wijnen site manager Richard de Boer. “Because the Ytong packs are already inside during the structural phase, they do not disrupt use of the construction hoist. We also don’t have to bring the packs inside using a material lift, which saves a considerable amount of time.” De Boer also describes the supply process as “much more efficient”. “The aerated concrete walls are supplied to size in labelled packs. Everything the wall installers need is ready on each floor. This reduces the number of transport movements, and there is little to no waste.”
Fit-out time cut by three months
Unlike other internal wall systems, the panels are not transported up afterwards using a construction hoist. This minimises the number of vertical and horizontal transport movements. Pre-positioning is estimated to cut fit-out time by as much as three days per floor on average. 2
Down to the centimetre
Peereboom of Xella says that preparing the smart collaboration required solving a complex puzzle. “The challenge was to position the packs precisely without clashing with the mechanical ventilation ducts and other building services. That is why the aerated concrete packs were placed on Ytong blocks exactly the same height as the foamed concrete screed to be poured. Once the floor had been poured and cured, the aerated concrete blocks were embedded in the screed, with the panels ready to be installed.” The position of the blocks was carefully coordinated with the pipework and included in the construction drawings. We even consulted Bestcon, the manufacturer of the precast walls, about the position of the braces and props, so that they would not be placed where our packs needed to go.”
The joint effort has delivered an impressive result: construction time for the entire project has been reduced by around three months. In addition to using Xella materials, Van Wijnen also chose Xella Construction Services to install the walls. This ensures both the quality of the materials and the workmanship.
De Hoge Regentesse is due for completion in early 2021.
Xella is the smart partner for building solutions in aerated concrete, calcium silicate and mineral insulation boards. As the global market leader in its sector, Xella helps partners across the construction chain build more sustainably, efficiently, to a higher standard and more simply. Xella does this by translating market knowledge and building regulations into innovative products and concepts, backed by extensive services. This portfolio of products and services gives partners a solution to meet the needs and requirements of today and tomorrow.
Vraag over dit verhaal? Stel je vraag
Wie eraan werkte
De Hoge Regentesse
- leverancierXella
- prefab wandenBestcon
- montage van de wandenXella Construction Services
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectDe Hoge Regentesse
- ThemaHoogbouw in beton en staal
- OnderwerpProjects
- BedrijfXella
- BedrijfBestcon


















