Projects

Structural anchor strengthens JuBi building

Tekst Roel van GilsFotografie Interboor

Stof- en trillingvrij boren met diamant tot in de drukzone van de te herstellen vloer. Het resultaat van scannen – karteren – van de obstakels in de te herstellen vloer is hier goed te zien.
Stof- en trillingvrij boren met diamant tot in de drukzone van de te herstellen vloer. Het resultaat van scannen – karteren – van de obstakels in de te herstellen vloer is hier goed te zien.

It quickly became clear that the collapse of the car park at Eindhoven Airport in 2017 would have far-reaching consequences. The Rijksvastgoedbedrijf, responsible for the Netherlands’ largest and most diverse property portfolio, with more than 13,000 properties, also had work to do. The entire portfolio has since been screened for potential hollow-core slab issues. Measures were found to be necessary at 21 properties, including the enormous JuBi building on Turfmarkt in The Hague. Interboor Midsland is currently strengthening the hollow-core slabs using the unique RAB anchor, while the building remains in use. 

With a gross floor area of 122,000 m2, the JuBi building is one of the larger buildings in the Rijksvastgoedbedrijf portfolio. The government office houses both the Ministry of Justice and Security and the Ministry of the Interior and Kingdom Relations, and was brought into use in 2013. “Shortly after the car park collapsed in Eindhoven, we launched an investigation. Initially, we focused on the most significant risks and examined buildings dating from after 2000,” says Rob van Rossum, programme manager at Rijksvastgoedbedrijf. “This produced a shortlist of several buildings with potential risks in the critical joints of their hollow-core slabs. The JuBi building and the court in Zwolle were the first to be addressed. The building in Zwolle has now been fully repaired, and the repair work at the JuBi building is well under way.”

‘State-of-the-art’ bespoke scanning device (designed by Terracarta of Hoogeveen) for scanning and repairing hollow-core slabs.

RAB team

Interboor Midsland is certainly an experienced specialist when it comes to repairing hollow-core slabs. “When the car park collapsed, we were working on the Voorzetgebouw Hoog Catharijne in Utrecht,” says Onno Dikkerboom of Interboor Midsland. “The office building was under construction at the time, using the same hollow-core slabs. To avoid having to strip out the entire building, Van Rossum Raadgevende Ingenieurs devised a structural anchor to strengthen the construction joint without adding extra reinforcement.” Interboor Midsland was asked to advise on the technical feasibility. “That gave us the distinction of strengthening the first building in the Netherlands with a structural anchor. Not long afterwards, working with the anchor supplier B+BTec, we developed the hollow-core slab renovation anchor (RAB) using the same principle. This is the method now being used here in The Hague.” Together with Van Rossum Raadgevende Ingenieurs, B+BTec, Verwol Interieur Realisatie and Warmtebouw Utrecht, TerraCarta completes the ‘RAB team’. Using its advanced scanning techniques, it determines the precise position of the anchors among the hollow-core cores, reinforcement and other obstructions. 

Visible on the right: a joint just scanned and mapped. On the left: a fully repaired joint with RAB anchors behind (almost invisible) bulkheads.

Low-noise and dust-free

The Rijksvastgoedbedrijf took its time and tested three strengthening methods at a trial site in Lelystad, before the tender phase for the JuBi building and the court in Zwolle. “The main aim of this trial was to assess the disruption caused by the different methods, so that we could take this into account when choosing a suitable repair method for the different buildings and their occupants,” says project manager Niels Andressen of the Rijksvastgoedbedrijf. “There is a structural defect, but it is not of a nature that puts the safety of building users at risk. The RAB method caused the least disruption. During the European tendering process, we then carried out a noise test on site, involving the staff council. They, too, concluded that this was the best method for the building.” Dikkerboom adds: “As well as being low-noise and dust-free, since we work with a closed system, our technique is extremely flexible. It can also be used in restricted, narrow spaces between the pipes and ducts beneath the ceiling. We can move fairly easily from one part of a building to another without causing too much disruption, allowing us to respond perfectly to the needs of building users.”

Diamond drilling rig

Despite the limited disruption, the Rijksvastgoedbedrijf chose to strengthen the building one floor at a time and clear most of each floor. “That simply makes things easier for everyone,” says Van Rossum. “In some cases, the floor joints are directly beneath a partition wall or ceiling island, which then have to be temporarily dismantled. We also take the opportunity to replace other equipment. This allows Interboor Midsland to work without interruption.” The work is progressing very smoothly. “This is already the ninth building we’ve repaired,” says Dikkerboom. “We’ve worked on almost every type and thickness of floor, with varying amounts of reinforcement and with or without concrete core activation. The calculations by Van Rossum Raadgevende Ingenieurs determine how many RAB anchors need to be installed. On site, we scan the underside of the floor and locate the drilling points, then use a diamond drilling rig to drill up to the compression zone of the floor. We then install the anchor, fill it with pure epoxy and tighten it to the specified torque. This restores the floor to its original design strength.”

Installed and fully assembled RAB anchors, before being concealed behind ‘invisible’ bulkheads.

Acid test

The method is self-checking. Dikkerboom explains: “The RAB anchor has an inspection hole. As the anchor is filled and tightened to the specified torque, a drop of epoxy (‘overflow’) emerges from the inspection hole. If no epoxy comes out, something has gone wrong and we reinstall the anchor. So the technique is ‘foolproof’.” At the JuBi building, a RAB anchor is installed approximately every 20 centimetres along the joints to be strengthened. In total, this amounts to around 50,000 anchors! Interboor Midsland began work in September 2021 and expects to remain active on Turfmarkt until spring 2023. “Over the past two years, we have developed the technique to the point where we can repair buildings of this size with a small workforce and a team of around six to eight people. Alongside the JuBi building, which is a wonderful reference project for us, we are strengthening several other buildings for different clients.” 

The RAB anchor causes relatively little disruption to the original ceiling finish, Van Rossum concludes. “We make as much use as possible of the existing bulkheads. If that is not possible, a new bulkhead is made in the same style. The calm atmosphere of the interior is therefore maintained after the work is completed.”   

Een zakelijke vraag aan Interboor Midsland? Neem contact op

Wie eraan werkte

JuBi-gebouw in Den Haag

  1. leverancier van het ankerB+BTec
  2. berekeningenVan Rossum Raadgevende Ingenieurs
  3. scantechniekenTerraCarta

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • ProjectJuBi-gebouw
  • OnderwerpProjects
  • BedrijfB+Btec
  • BedrijfVan Rossum Raadgevende Ingenieurs
  • BedrijfTerraCarta
  • BedrijfInterboor Midsland
Deel dit artikel

Advertentie

Volgen op Beton & Staalbouw

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.