Working together to solve structural puzzles in the repurposing of the Zeeburgereiland silos
Tekst Tjerk van DuinenBeeld Pieters en Elephant

In 2006, a new facility in the Western Port Area took over the work of Rioolwaterzuivering Oost on Zeeburgereiland. Since then, the Sportheldenbuurt development has been taking shape on the site. Most of the silos have been demolished, and only three large silos remain as reminders of the former wastewater treatment plant. Many plans for repurposing them have come and gone over the years, until the ‘Drie Koningen’ plan by Vink Bouw Nieuwkoop and Grayfield Management was given the green light by the municipality of Amsterdam in 2017. Designed by architectural practice Elephant, the industrial heritage is being converted into multifunctional facilities and topped with an impressive superstructure. Pieters was given the challenge of solving this structural puzzle.

Several options for the site’s redevelopment were considered, including a hotel. The end result, however, will be a range of multifunctional facilities that will be a welcome addition to the new residential neighbourhood. Rialto will operate a cinema in the westernmost silo, the middle silo will house a gym and the eastern silo will become a restaurant. An existing walkway, 25 metres above ground, will link the three facilities as a rooftop park. Office space is planned on the upper floors.

19 metres of sediment
The structural design for this repurposing project includes several interesting solutions. These mainly involve adapting a structure to changed loads and transferring them to the foundations. Pieters, which had already been involved as structural engineer during the tender phase, was tasked with solving the puzzle. “The starting point was three silos built in 1978, each 19 metres high and 21 metres in diameter,” says Tim Kooij, structural engineer at Pieters. “They were built as settling tanks, with a 50 cm thick floor on a pile foundation arranged in a concentric pattern. The walls are made of concrete and are 35 cm thick. Horizontal forces are resisted throughout the height of the walls by prestressing cables, anchored at six points in thickened sections containing spiral reinforcement. As a result, each silo has six vertical thickened sections, or pilasters. Surveys in 2017 and 2023 found the structures to be in good condition.”

Rerouting the forces
With these parameters established, Pieters had to find ways to adapt the silos to their new functions, with the added storeys in particular introducing new loads. Kooij: “We are moving from a uniform floor load of 66,000 kN of sediment to a superstructure whose loads had to be transferred almost entirely to the silo wall. We therefore designed the same steel structure for all three silos and worked it out in detail together with Buiting Staalbouw. The base is a table structure bearing on the six pilasters, with a 5-metre-high truss underneath. The steel stability core and a neck structure rest on this base, supporting the three office floors. This transfers most of the forces to the silo wall; the remainder is carried by two columns beneath the core structure, alongside the access points. The table structure is at the level of the future rooftop park, which will be connected by walkways. That means you can have a bite to eat across the way and then catch a film.”

Recesses
Without additional structural measures, almost the entire load would be transferred via the wall to the piles directly beneath it. To bring the other piles into play as well, a large number of openings were cut into the bottom of the wall, and a 70 cm thick floor was cast on top of the existing one. Dowels ensure that the old and new floors act together structurally. Kooij: “The recesses mean that the silo wall also bears on the new floor, which is now 120 cm thick. Cutting the openings was not straightforward because the wall is 35 cm thick, and more than 60 cm thick where the pilasters are located. Fortunately, the prestressing strands are fully bonded, so we could simply cut through them. The recesses and the strengthened floor, with its heavy reinforcement, allow us to transfer the load from the wall towards the centre. The columns beneath the core structure stand on base plates anchored to the new floor. Ultimately, the aim is to ensure that the total load does not exceed 66,000 kN, and we have achieved that.”

Cinema auditoriums
The openings have now been made, the floor has been cast and the steel structures installed in the silos. At the beginning of April, the first truss was lifted into position. “This substantial 5-metre-high truss makes it possible to build two cinema auditoriums without columns,” Kooij explains. “This silo has internal floors, which will accommodate smaller auditoriums. The floor slabs are fixed to the silo wall. We are using Comflor 95 and Comflor 210 composite steel deck floors. The same applies to the sloping cinema floors on which the seats are installed.”

Half-moon
Structurally, the silos housing the gym and restaurant have been designed in the same way as the western silo with the cinema. The restaurant differs in that one floor is shaped like a half-moon. It will also have an additional lift for goods transport. At the gym, the operator asked for a continuous wall to be kept clear for installing exercise equipment. “All in all, this is a fantastic project, and soon there will be a beautiful complex here,” Kooij concludes enthusiastically. “Repurposing projects like this are really enjoyable puzzles, which you solve together as a structural engineer with the client, users, architect, contractor and suppliers.”
Composite steel deck floors for the silos
All the silo floors will be made using ComFlor composite steel deck floors. The system offered plenty of advantages for structural engineer Pieters to incorporate it into the design. “First and foremost, because of the design flexibility ComFlor offers,” explains Wiebren Wind of Dutch Engineering. “The buildings are circular, some of the floors are sloping and there are many interruptions caused by the steel structures. That would be much more difficult to achieve with hollow-core slabs. The overall weight of the new structure is also a major consideration. Here, ComFlor’s lower self-weight compared with the alternatives worked in our favour. A third reason is that the contractor can work without propping with the selected composite steel deck floors.”
Buiting Staalbouw, responsible for the complete steel structure, is using three types of composite steel deck floor. Wind: “For the silo fit-outs and cinema floors, this involves 2,700 m2 of ComFlor 95 and 300 m2 of ComFlor 100. A total of 5,400 m2 of ComFlor 210+ is being used for the office floors in the silo superstructures. This is our updated type, with a profile that allows the steel deck to contribute even more effectively as bottom reinforcement. This makes longer spans possible. The concealed fixings also mean the decks can be left exposed.” The steel decks were manufactured in Zoeterwoude. They are cut to size using a cutting robot at Buiting’s factory, helping to shorten the construction programme.
Een zakelijke vraag aan Dutch Engineering? Neem contact op
Wie aan de silo's op het Zeeburgereiland werkte
- architectenbureauElephantIn dit verhaal
- constructeurPietersIn dit verhaal
- totale staalconstructieBuiting StaalbouwIn dit verhaal
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectSilo's Zeeburgereiland
- ThemaBouwen in de bestaande stad
- OnderwerpProjects
- BedrijfElephant
- BedrijfPieters
- BedrijfBuiting Staalbouw
- BedrijfDutch Engineering



















