Utrecht RIVM/CBG | Intensive concrete work at Utrecht Science Park

Construction of the new premises for the National Institute for Public Health and the Environment (RIVM) and the Medicines Evaluation Board (CBG) once again gave RED Betonbouw an excellent opportunity to put its extensive knowledge and expertise into practice. Drawing on its diverse experience, the VCA*-certified concrete specialist used top-quality materials, equipment and manpower to deliver the complete substructure of the 18-storey building. The work was completed without any significant problems and, according to site manager Jaap Troost, was intensive, wide-ranging and great fun to do.
Since its foundation in 2010, RED Betonbouw has steadily built a reputation for delivering a wide variety of concrete works for both residential and non-residential construction. The successful project at Utrecht Science Park was therefore a perfect fit for the Oud-Beijerland-based company. Marin Medic, work planner at RED Betonbouw, agrees. “Over 2018 and 2019, working for main contractor MEET RIVM CBG B.V. (MEET, ed.), our dedicated site team completed the entire substructure of the building up to ground-floor level in a total of 40 weeks. In broad terms, that included the basement floors and walls, as well as the ground-floor slabs. It was a project perfectly suited to our capabilities, and one in which we were able to apply our expertise across the board.”

The 1.80-metre-high floor formwork, traditionally braced against two rows of concrete blocks in the sand. A welded reinforcing bar was installed behind it to prevent the formwork from sliding.
Traditional construction
Among other works, RED Betonbouw was responsible for pouring a massive foundation block 1.80 metres high, with an area of more than 3,000 m2 and a volume of no less than 5,445 m3. External walls 600 millimetres thick were built on top of the foundation block. The concrete structure was designed to fully meet the specified vibration requirements. “Instead of using wall formwork, we formed the entire floor using traditional formwork,” says Troost. “This was because of the less than ideal conditions on site, particularly the limited space and the ground conditions. It is also worth mentioning that we poured the floor in a single operation using four concrete pumps, to prevent cracking as a result of the large volume of concrete.”

Reinforcement for the 1.80-metre-high foundation block. The buttresses and traditional formwork for the block are shown on the right.
Double benefit
To speed up the installation of the formwork, work more flexibly on site and drastically reduce the number of square metres of semi-precast floor slabs, RED Betonbouw opted to combine U-Bahn boxes with floor formwork instead of using semi-precast floor slabs. “The original plan was to construct the entire floor using semi-precast slabs incorporating the U-Bahn boxes. In the end, we opted for a combination with floor formwork. This decision brought a double benefit. On the one hand, it reduced the number of square metres of semi-precast slab; on the other, it delivered a substantial reduction in weight,” says Medic, before highlighting the other works carried out by RED Betonbouw. “The buttresses we installed were built using a combination of MAXIMO wall formwork and traditional formwork. They make for a very impressive sight.”
For more information about this project, visit
Vraag over dit verhaal? Stel je vraag
Wie aan de nieuwbouw van RIVM en CBG werkte
- ontwerp en de realisatie van het gebouwMEET StruktonGenoemd in RIVM/CBG, Utrecht | New RIVM/CBG building stands firmly in place
- hoofdaannemerStruktonGenoemd in Utrecht RIVM/CBG | Versatile foundation expertise delivers a vibration-free building
- de complete bouwputFranki GrondtechniekenGenoemd in Utrecht RIVM/CBG | Versatile foundation expertise delivers a vibration-free building
- stort van een massieve vloerpoerRED BetonbouwIn dit verhaal
- glijbekistingGleitbauGenoemd in utrecht RIVM/CBG | Four reinforced concrete cores for striking tower building realized using sliding formwork
- glijbekistingGleitbau Ges.m.b.HGenoemd in utrecht RIVM/CBG | Four reinforced concrete cores for striking tower building realized using sliding formwork
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectNieuwbouw RIVM/CBG
- OnderwerpProjects
- BedrijfRED Betonbouw



















