Utrecht RIVM/CBG | Versatile foundation expertise delivers a vibration-free building

Every foundation project calls for a specific approach and expertise. This was once again evident when construction of the new accommodation for the National Institute for Public Health and the Environment (RIVM) and the Medicines Evaluation Board (CBG) came under scrutiny. Franki Grondtechnieken delivered the complete excavation pit for the 18-storey building at Utrecht Science Park. An impressive achievement that once again underlines the multidisciplinary nature of the foundation specialist, founded in 1909.

CSM wall.
Flexible, results-driven, innovative. The expertise offered by Franki Grondtechnieken has many facets. Above all, however, the company stands out for the range of foundation solutions and associated know-how it offers in the most varied situations. “Alongside extensive advisory capabilities, we offer a broad range of disciplines,” says director Jan-Wim Verhoeff on behalf of Franki Grondtechnieken, which has been part of the BESIX GROEP since 2009. “This enables us to select the most suitable technique for every project. We are particularly specialist when it comes to large, heavy structures and working in sensitive environments. Think, for example, of urban and petrochemical projects, where work often has to be carried out with low levels of vibration and noise. To ensure the best possible outcome, however, it is preferable for our company to be involved at the very earliest stage of a project. Taking into account the client’s requirements, the available budget, the soil type and conditions, and the surrounding environment, we present the client with the advantages and disadvantages of the possible techniques, enabling an informed choice to be made. It is even possible to combine different techniques. We have all the necessary knowledge and expertise in-house.”

Anchor beam with grout anchors.
Combining techniques
A striking example of Franki Grondtechnieken’s broad range of expertise delivering an optimal end result is the construction of the new premises for the National Institute for Public Health and the Environment (RIVM) and the Medicines Evaluation Board (CBG), due to be completed as planned in autumn 2021 at Utrecht Science Park. “The RIVM uses high-end laboratory equipment that is extremely sensitive to vibration,” Verhoeff explains. “It is therefore vital that the new accommodation is built in such a way that vibration does not interfere with the equipment. After main contractor Strukton commissioned us to deliver the complete excavation pit, we met that requirement in full.”

Large-diameter bored piles (diameter 1,850 mm, depth 58 m).
Following expert advice at the preliminary stage, Franki Grondtechnieken completed, in just six months, the soil mix (CSM) walls, concrete work, anchoring, ground injection, foundation piles, pile-head trimming and all earthworks, among other tasks. The end result was an excavation pit measuring 80 x 160 metres, from which the building is now steadily rising. “In most cases, we are brought in as a specialist subcontractor, but on this occasion we took on the project from A to Z,” says Verhoeff. “The client did not have to worry about a thing. The work delivered in Utrecht is therefore a clear demonstration of the wide range of techniques with which we can serve the market through our bespoke offering.”

Installing an anchor beam on a CSM wall.
Vraag over dit verhaal? Stel je vraag
Wie aan de nieuwbouw van RIVM en CBG werkte
- ontwerp en de realisatie van het gebouwMEET StruktonGenoemd in RIVM/CBG, Utrecht | New RIVM/CBG building stands firmly in place
- hoofdaannemerStruktonIn dit verhaal
- de complete bouwputFranki GrondtechniekenIn dit verhaal
- stort van een massieve vloerpoerRED BetonbouwGenoemd in Utrecht RIVM/CBG | Intensive concrete work at Utrecht Science Park
- glijbekistingGleitbauGenoemd in utrecht RIVM/CBG | Four reinforced concrete cores for striking tower building realized using sliding formwork
- glijbekistingGleitbau Ges.m.b.HGenoemd in utrecht RIVM/CBG | Four reinforced concrete cores for striking tower building realized using sliding formwork
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectNieuwbouw RIVM/CBG
- ThemaStil en emissievrij bouwen
- OnderwerpProjects
- BedrijfStrukton
- BedrijfFranki Grondtechnieken