Michiel de Ruyter Bridge: A structural challenge
Tekst Roel van GilsFotografie Ingenieursbureau Boorsma

The Michiel de Ruyter Bridge is anything but a standard bascule bridge. To be fully prepared at tender stage, construction consortium 2KA brought in the expertise of Ingenieursbureau Boorsma at a very early stage. The specialist in movable bridges worked with the consortium to turn ingenious structural ideas into a buildable solution. Together with Anne Jan Breimer of Ingenieursbureau Boorsma, we take a closer look at three technical challenges.
Ingenieursbureau Boorsma has extensive experience in the engineering of movable bridges of all shapes and sizes. “Our projects range from small bascule bridges for cyclists and pedestrians to huge schemes such as the bascule bridges at Sluis Terneuzen,” says Breimer. The Michiel de Ruyter Bridge is a special project for the firm in several respects. “First, the bridge is being built just a stone’s throw from our office in Urk. In addition, our scope for this bridge is quite extensive. For Knipscheer Infrastructuur, we carried out the engineering of the civil substructure and the fendering and guide structures, and for Knook Staal en Machinebouw, the engineering of the steel construction and the mechanical systems.”

Load transfer
According to Breimer, the advantage of such a broad scope is that everything can be handled in-house. “Coordination at the interfaces is then relatively straightforward. Our main task was to meet the requirements of the visual quality plan as effectively as possible, within the stipulated parameters and the consortium’s EMVI commitments. One of these was to build in the water without a cofferdam, a deliberate choice to minimise disruption to shipping. Our firm was already familiar with this method, having worked on a similar concept for the Vechtbrug.”
The ‘cofferdam-free construction concept’ for the Michiel de Ruyter Bridge involved positioning a 115-tonne precast base for the bridge pit on the steel tubular piles in the water. A concrete floor was then cast, interlocking ingeniously with the precast structure and playing a key role in transferring the overall forces from the kingpost and cylinders to the steel tubular piles. “This meant a substantial amount of reinforcement was needed locally.”

Camber
The visual quality plan had already specified a central kingpost with a single tie rod. “This naturally brings its own challenges, particularly in the design and construction,” Breimer explains. “For example, we calculated how much camber (pre-deformation) Knook Staal en Machinebouw had to build into each of the two bascule leaves in the factory to ensure that the bearings would be under compression in the final situation. The aim was to guarantee stable seating and prevent the leaves from rattling. To ensure that the pre-deformation had been incorporated correctly, Knook Staal en Machinebouw carried out a full-scale test in the factory. The pre-deformation is eliminated as the leaves rise.”
The additional weight of approximately 6 tonnes also contributes to positive bearing pressure. “That extra weight is possible because the bridge has a hydraulic drive, with a separate cylinder for each leaf. When the bridge is closed, the cylinders do not need to be pressurised. The cylinders are sized to suit the different surface areas of the two leaves. This keeps the pressure in the system more or less equal, so a single hydraulic power unit is sufficient.”
Ingenieursbureau Boorsma produced almost 150 drawings for the Michiel de Ruyter Bridge, all of them based on a 3D model. “In the end, we also added ÆVO’s scope to the model. ÆVO was responsible for the electrical installations. This resulted in an integrated 3D model, which we can now conclude was the basis for a successful construction project. It is a wonderful reference and, quite literally, a home game for our firm.”
Vraag over dit verhaal? Stel je vraag
Wie aan de Michiel de Ruyterbrug werkte
- civiele gedeelteKnipscheer InfrastructuurGenoemd in Michiel de Ruyter Bridge: Civil engineering highlights
- specialist in beweegbare bruggenIngenieursbureau BoorsmaIn dit verhaal
- elektrotechnische installatiesÆVOIn dit verhaal
- staalbouwKnook Staal en MachinebouwIn dit verhaal
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectMichiel de Ruyterbrug
- OnderwerpProjects
- BedrijfIngenieursbureau Boorsma
- BedrijfÆVO
- BedrijfKnook Staal en Machinebouw


















