Michiel de Ruyterbrug: an icon in the Urk landscape
Tekst Roel van GilsFotografie Bouwcombinatie 2KA

Construction company 2KA is hard at work building a third bridge over the Urkervaart in Urk. The Michiel de Ruyterbrug is essential to Urk’s future, connecting the new Zeeheldenwijk with the rest of the fishing village and improving accessibility across Urk. As well as its striking design and the challenges involved in making it buildable, the collaboration between the Municipality of Urk as client and the Province of Flevoland as ‘consultancy’ is also admirable.

Urk is continuing to grow rapidly eastwards. “Because people believe they have to make a detour, the municipality has long wanted to build a third road bridge over the Urkervaart,” begins Dick van der Snee, civil engineering project leader at the Municipality of Urk. “The first steps were taken back in 2006, in conjunction with the construction of a new ring road. These plans came back to the fore around 2017, when the go-ahead was given for the Zeeheldenwijk, a completely new residential area. Some of the cost of the new bridge could be offset against the land development costs.”

Joining forces with the project team
Urk currently has two movable bridges over the Urkervaart: the Zwolsebrug and the Arie de Witbrug. The former is a footbridge and cycle bridge dating from 2006, while the Arie de Witbrug, which carries road traffic, dates from 1989. The bridges belong to the municipality, but are operated by the Province of Flevoland. “We have been working with the Municipality of Urk on bridge and lock operations for 33 years,” says Bart Jansen, project manager at the Province of Flevoland. “Initially, operations were managed from the control room at the Urkersluis, and since 2014 they have been controlled remotely from the provincial offices in Lelystad. The municipality’s plans to build the Michiel de Ruyterbrug coincided almost exactly with our plans for major maintenance on all provincial bridges and locks. We asked the municipality if it would like to join the contract for major maintenance on the Zwolsebrug and the Arie de Witbrug. At the same time, the municipality asked the province to make use of the expertise of the project team at the provincial offices in drawing up the contract for the Michiel de Ruyterbrug, which we will also operate once it is complete.”
Visual quality plan
The Province of Flevoland proposed delivering the Michiel de Ruyterbrug under a UAV-GC contract, just like the renovation contract for the provincial bridges and locks, Van der Snee continues. “That was quite a big challenge for us as a small municipality. We were keen to have ‘a say’ in the bridge design. It had to be a landmark, a recognisable gateway to the village. That led to the idea of using a visual quality plan. We brought in an architect who developed a large number of options. In the end, two visual quality plans were drawn up: one for the bridge itself and one for its surroundings, including the roundabout, roads, planting and landscape design. All of this was incorporated into a UAV-GC contract, which led to a European tender.” Following preselection, five bidders remained. In the summer of 2020, the contract was awarded to construction company 2KA on the basis of EMVI, comprising Knook Staal en Machinebouw, Knipscheer Infrastructuur and ÆVO.

Winning on EMVI
“We won the tender on quality,” says Edwin Raats, project manager at Knook Staal en Machinebouw and lead partner on behalf of construction company 2KA. “We beat the lowest-priced bids by scoring well on EMVI. During the tender, we came together as a team. We assessed the site and, on that basis, drew up a plan and made commitments on limiting disruption to the surrounding area, protecting flora and fauna, and reducing project risks. The latter included the fact that there was no electricity supply at the time. We therefore introduced a risk control measure, using a peak shaver to reduce the power drawn. We also visualised the bridge’s movement and control system at an early stage using a 3D model and digital twin, to avoid surprises during construction. We deliberately assigned the civil and mechanical engineering work to a single engineering firm, specifically to manage interfaces and benefit from having one design and one 3D model.”

A flowing line
The distinctive design, with a flowing line from the concrete approach bridge to the steel bascule leaf, and the rounded forms of the steel counterweight and lifting tower, proved difficult to achieve. Only a handful of factories in the Netherlands can roll and bend components for a design of this kind. The eccentric connection of the suspension rod to the bascule leaf also posed a challenge. “The road bridge leaf is larger than the cycle bridge leaf, but the two are connected. The suspension rod is attached at that connection. This causes a degree of deformation that can really only be assessed in the final configuration,” Raats explains. “However, it has to fit the concrete, which is built earlier, with 100% accuracy. The challenge was to avoid significant dimensional deviations. We largely addressed this by applying (deformation) calculations to the 3D model and postponing the final concrete pour until both bridge leaves had been installed. Together with Knipscheer, we put the necessary control measures in place, continuously checking each other’s steps during construction. And it has worked well. We are nearing the end of the construction phase and can now cautiously conclude that there have been no major surprises.”
The project has also been a success for the municipality and the province so far. “We could just as easily have drawn up a RAW specification or a UAV-GC contract with a consultancy, but that would have led to a different approach,” concludes Van der Snee. “This project was built around extensive collaboration, because after handover the municipality, as owner of the bridge, and the province, which is responsible for its operation, will continue working together. There are many more factors involved than simply handing over a bridge and overseeing its construction. This kind of collaboration also makes it easier to obtain permits, thanks to our respective networks.” The Michiel de Ruyterbrug will be officially opened in early 2023. It will be the third bridge over the Urkervaart, but according to Van der Snee, not the last. No doubt there will be more to come!
Vraag over dit verhaal? Stel je vraag
Wie aan de Michiel de Ruyterbrug werkte
- opdrachtgevergemeente UrkIn dit verhaal
- bouwcombinatie2KAIn dit verhaal
- civiele gedeelteKnipscheer InfrastructuurGenoemd in Michiel de Ruyter Bridge: Civil engineering highlights
- specialist in beweegbare bruggenIngenieursbureau BoorsmaGenoemd in Michiel de Ruyter Bridge: A structural challenge
- bouwcombinatiebouwcombinatie 2KAIn dit verhaal
- adviesbureauprovincie FlevolandIn dit verhaal
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectMichiel de Ruyterbrug
- ThemaBruggen en kunstwerken langer mee
- OnderwerpProjects
- Bedrijfgemeente Urk
- Bedrijf2KA
- Bedrijfbouwcombinatie 2KA
- Bedrijfprovincie Flevoland
- BedrijfJansen B.V.


















