Van Brienenoord Bridge: a fascinating interplay of timber and steel
Text Roel van GilsImage Rijkswaterstaat

Replacing 395 timber beams and 5,200 bolts
The Van Brienenoord Bridge is more than half a century old. The busiest bridge in the Netherlands ‘guides’ more than 230,000 vehicles across the Nieuwe Maas every day. Most of them cross a very unusual structure without giving it a second thought. The eastern bascule span is characterised by a fascinating interplay of timber and steel. And that is precisely where the problem lay. Water had seeped into the timber beams of the bascule span through the cracked wearing course. This ultimately led to an initial repair operation in June 2024, which was halted prematurely when the situation proved more serious than anticipated. After thorough preparation, 395 beams and 5,200 bolts were replaced over the long weekends of Ascension Day and Whitsun, ensuring the bridge remains safe and available until the major renewal planned from 2029 onwards.
Rijkswaterstaat faces a huge task. Many bridges, tunnels, viaducts and roads were built in the 1950s and 1960s and are now due for major refurbishment or even complete replacement. This cannot all be done at once. To save time, Rijkswaterstaat in South Holland has set up the Over-Bruggen team, with the aim of carrying out essential major maintenance on 20 steel movable bridges until they are replaced or refurbished. The Van Brienenoord Bridge is one of them. It consists of two parallel arch bridges, followed by three bascule bridges. The eastern arch dates from 1965. The western arch is much newer, having been built in 1990.

Wetter than expected
The Over-Bruggen team takes a critical look at each structure to assess which components need attention to ensure the bridge remains safe and available until it is replaced or refurbished, says Menno Kamp, environment manager at Rijkswaterstaat. “During the inspection of the Van Brienenoord Bridge, damage was found to a number of timber beams in the eastern bascule span, caused by cracks in the wearing course. A repair operation was therefore launched. Initially, the plan was to replace only the 13 beams that were in poor condition at the time, and to replace the bolts on all the beams because they were severely worn. During the repair work in June 2024, removing those beams also damaged adjacent beams. Jacking out the bolts also caused damage to neighbouring beams. This was because the beams were much wetter than originally estimated.
As the wearing course on the beams had become porous, water had penetrated deep into the timber. Given the damage to adjacent beams and the worse-than-expected condition of the beams, it was decided to halt the work and repair the wearing course as thoroughly as possible using ‘spot repairs’, to stabilise the situation. A plan was then devised for a permanent repair. A smart and creative approach was needed to carry out the work as efficiently as possible, with minimal disruption and risk of overrunning.”

Hexavalent chromium
It was decided to carry out the repair work during the long, consecutive weekends of Ascension Day and Whitsun in 2025. “The scope involved replacing 395 Azobé beams, each weighing 200 kg, replacing 5,200 bolts and replacing the asphalt beneath the arch bridge and on the roof of the caisson,” says Erwin Kommeren, technical manager at Rijkswaterstaat. “To prepare, a suspended scaffold was first built beneath the movable section of the bascule span so that the bolts could be removed. The preparations also incorporated all the lessons learned from the repair work in June 2024. The bolts turned out to be extremely rusty. Cutting them off with a bolt cutter was time-consuming and far from efficient. The idea was therefore proposed of cutting through them with an angle grinder. However, the coating contained hexavalent chromium. It was therefore decided to remove all the protective coating and corrosion under controlled conditions before the first weekend.”

Drilling stations
After abrasive blasting, the bolts could be cut through during the two planned weekends, shortly before the old beams were removed, without any additional health and safety measures. “Grinding above shoulder height is physically demanding and increases the risk of accidents and damage to the existing structure,” says Kommeren. “We therefore developed special hanging brackets that could be fitted between the longitudinal girders supporting the timber, so that the angle grinder only had to be turned into the bolt. This meant that the critical path was no longer determined by removing the bolts, but by reinstalling the beams. We also had to speed this up, because two (long) weekends were not enough to install 395 new beams using traditional methods. At the Van Brienenoord Bridge, each bolt hole is positioned individually on the beam. The new beam must therefore first be positioned so that the bolt holes can be marked. It is then removed again to drill the 12 holes, after which it can be put back in place and secured. This is also physically demanding work, with machines jamming and drill bits wearing out quickly. We streamlined the process by setting up two trailers as drilling stations, complete with an overhead gantry crane, roller conveyors and drilling machines mounted in stands. The drilling stations not only enabled us to significantly increase the rate of work, but also made the job much less physically demanding. We received a lot of positive feedback from the people who carried out the work.”

Wearing course
To protect the timber beams against moisture ingress and provide sufficient skid resistance, a wearing course is applied after installation. “The wearing course has to be built up in two layers, and application is highly sensitive to weather conditions. The first layer also needs around 4 to 5 hours to dry before the second can be applied. This is hardly conducive to shortening the programme, which was already very tight,” says Kommeren. “We optimised this process too by applying the first part of the wearing course to the beams at the sawmill. That saved us an entire drying cycle and a lot of time on the bridge. After the bolts had been installed, the bolt holes were filled with epoxy, after which the second and final part of the wearing course was applied and dressed with gravel. Saw cuts a few millimetres deep were then made in the wearing course to initiate any potential cracks precisely along the joints between the beams. Finally, a new asphalt layer was laid.”
“One thing we noted during the repair work was that the steel is still in relatively good condition. No additional major maintenance is required until the bridge’s long-term preservation works,” says Kommeren. The bridge will be maintained continuously until it is replaced or refurbished, to ensure that it remains safe and available. The Over-Bruggen team has already moved on to the next structure. “Over the next ten years, we will tackle two structures a year in this way,” says Kamp. “Our focus is now on the Algerabrug and Merwedebrug. At the Algerabrug, we will also replace the timber beams, but the underlying steel will need work too. This means the project will take considerably longer than the two weekends we needed at the Van Brienenoord Bridge.”
Question about this story? Ask your question
Who worked on the renovation of the Van Brienenoordbrug
- blast cleaning the steel structureStraal- en Schildersbedrijf FeijenoordMentioned in Stronger together at the Van Brienenoord Bridge
- hydraulic engineering specialistNobel Waterwerken BVMentioned in ‘Carrying out this job safely and efficiently is a shared goal’
Keep following this
Get an email when a new story is published. No account needed.
- ProjectVan Brienenoordbrug renovation
- ThemeMaking bridges and civil structures last longer
- SubjectProjects


















