Transformation of the Van Gendt Hallen, Amsterdam

The Van Gendt Hallen on Amsterdam’s Oostenburg island were long a symbol of industrial innovation. The five huge interconnected halls were built in 1886 by the Koninklijke Nederlandsche Fabriek van Werktuigen en Spoorwegmaterieel, later known as Werkspoor, to a design by A.L. van Gendt. Countless steam locomotives and, later, diesel engines were built here, until the last diesel engine left the Stork-Werkspoor-Diesel factory in 1995. If local residents had not protested against the demolition plans, the halls would no longer be standing. The complex is now a listed national monument, and its owner, Eduard Zanen, has ambitious plans for the Van Gendt Hallen. 

Impression of the gantry at the VOC quay. (Image: Van Gendt Hallen)

The gross floor area of the five interconnected halls will increase from 13,000 m2 to 25,000 m2 as a result of the transformation. In this recently densified part of the city, Zanen is creating a high-impact programme rooted in innovation, with offices, hospitality venues, sustainable start-ups and scale-ups, several homes and the Drift Museum. The museum will have 8,000 m2 for large-scale, mostly experimental art involving moving images and installations. The project is being delivered with careful preservation of the site’s monumental and industrial character. 

Architecture firm Braaksma & Roos Architecten redeveloped the building. Its acclaimed transformation of the LocHal in Tilburg had impressed Zanen. “Old artefacts such as inspection pits, crane rails and colourful patina were left intact there, which the client was very enthusiastic about,” says project architect Christina Kaiser. “The Van Gendt Hallen, too, are full of signs of use, old machinery, shafts, pipes and crane rails. In addition, the industrial functions led to frequent alterations: new openings were made in the brick façades, doors were moved and roofs were adapted. So the building envelope has evolved over time. We are leaving it intact and have restored it where necessary. The steel crane rail and truss structures, along with all the industrial machinery, have now been cleaned and otherwise treated as little as possible.”

Roof profile

The distinctive steam cowls have been reinstated along the ridges of four of the five halls, restoring the complex’s original roof profile. Made from a composite of bio-resin and recycled PET bottles, they are not only sustainable and fire-safe, but the material is also light and strong enough to support solar panels. At the same time, the rooflights, which had also been replaced or sealed over, have been returned to their original positions. Vacuum glazing in the restored cast-iron frames provided a slender solution that was not too heavy. The old pumice concrete slabs in halls 4 and 5 have been left exposed, with recycled composite, insulation and roofing installed on top.

The steel crane rail and truss structures, along with all the industrial machinery, have now been cleaned and otherwise treated as little as possible. (Image: Colina van Bemmel)

Fit-out on floors

Meanwhile, all the old hall floors have been replaced with floors incorporating thermally activated building systems and ground storage. The floor itself is not insulated, but the façade below ground level is insulated with EPS. The floor and the ground beneath it therefore act as a buffer, maintaining a stable indoor temperature and saving around 20% on heating. Kaiser says: “It was an idea from sustainable innovation developer Jorrin Janssen, and it fits well with the halls’ innovative history. Steel and timber structures, using sustainable CLT (editor’s note), have been built on these concrete floors to accommodate fit-outs of between one and four storeys. The heritage vision developed by Braaksma & Roos, which also focused on enabling a diverse range of uses, has been translated into a spatial design. Javier Zubiria developed and refined the design further. It is not a box-in-box solution, but more like a second skin with a very large cavity. This leaves the monumental envelope intact and creates a comfortable climate in the fit-out, while the cavity itself is also a pleasant space to be in.”

Part of the city

The Van Gendt Hallen will not only provide a splendid setting for their users, but also become a carbon-neutral industrial monument on an unprecedented scale. “On top of that, Eduard Zanen and I want to anchor the building in the urban fabric of Oostenburg,” Kaiser explains. A small railway line once ran through all five halls, carrying a kind of tipper wagon. It has been widened and will become the building’s central cross-axis: a pedestrian route running from Oostenburgermiddenstraat through the complex to the gantry at the VOC quay. From here, visitors can experience the halls’ impressive height. The gantry will become part of the public realm, where people can have coffee during the day and events can be held. Another distinctive feature is that the gantry extends from the halls over the quay and spans the new marina basin. This will give the Van Gendt Hallen the option of establishing a boat connection with the city and Central Station.   

Question about this story? Ask your question

Who worked on the Van Gendt Hallen

  1. redeveloped the buildingBraaksma & Roos ArchitectenIn this story
  2. steelwork contractorVic ObdamMentioned in 800 tonnes of new steel for Van Gendt Hallen
  3. structural engineerSophia EngineeringMentioned in 800 tonnes of new steel for Van Gendt Hallen
  4. composite steel and concrete floorTullingh & PartnersMentioned in Construction team opts for composite steel deck floors
  5. sheet pilingHeicombinatie SPSMentioned in A matter of flexibility
  6. reinforcementP. de BoorderMentioned in Standing out with an unsexy product
  7. ownerEduard ZanenMentioned in A matter of flexibility
  8. steelwork contractorVic Obdam StaalbouwMentioned in 800 tonnes of new steel for Van Gendt Hallen
  9. project teamVan Gendthallen BVMentioned in 800 tonnes of new steel for Van Gendt Hallen
  10. reinforcing steelP. de Boorder & ZoonMentioned in Standing out with an unsexy product
  11. Architectural practiceBraaksma & RoosMentioned in The Van Gendt Hallen in Amsterdam-Centrum Oost: from nostalgic factory hall to stylish energy-positive icon

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectVan Gendt Hallen
  • SubjectProjects
  • CompanyBraaksma & Roos Architecten
Share this article

Advertisement

Follow on Beton & Staalbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.